Keystone prepares early data-centre site studies for India and the USA. Most site decisions turn on a few checks. Doing them in the right order saves spend on sites that will not work.
The order of checks
- Power date and phases. When can power arrive, how much, and in what steps? A nearby line or substation is a lead to verify, not a connection. Only the serving utility's written answer counts.
- Permission route. Is a data centre allowed by right, by special permit, or not at all in this district?
- Usable land. What remains after setbacks, easements, flood areas and access, and does it fit the halls and plant you need?
- Water and cooling. What supply and discharge the cooling design needs, and what is confirmed.
- Access and fibre. Road access for construction and equipment, and carrier routes.
- Cost, timeline and returns. Only after the checks above, because each one moves these numbers.
What the study gives you
A comparison of campus options for the site, with power needs, cost range, timeline and estimated returns. Each finding is marked measured, assumed or not checked, so your team sees what to verify next.