Data centre site selection in India: what to check

By , Founder, Keystone AEC (keystoneaec.com)

Keystone prepares early data-centre site studies for India and the USA. In India, a few checks decide most sites. Doing them in order saves spend on land that will not work.

Illustrative card; not a real site
Illustrative editorial image; it does not show a real site.

The checks, in order

  1. Power date and phases. Ask the state distribution company or transmission utility when power can arrive, how much, and in what steps. A line or substation nearby is a lead, not a connection.
  2. State policy. Read the current data-centre or IT policy for the state. It sets incentives, approval routes and which land qualifies.
  3. Land use and building rules. Confirm the parcel's land use allows a data centre. Then apply the local development control rules: setbacks, ground coverage, FSI and height. Industrial land is a start, not a yes.
  4. Water and cooling. Find the supply source and the discharge route the cooling design needs, and what is confirmed in writing.
  5. Seismic and flood risk. Note the seismic zone under IS 1893 and check flood history and drainage for the plot.
  6. Access and fibre. Road access for heavy equipment, and the carrier routes near the site.
  7. Cost, timeline and returns. Only after the checks above, because each one moves these numbers.

What the study gives you

A comparison of campus options for the site, with power needs, cost range, timeline and estimated returns. Each finding is marked measured, assumed or not checked, so your team knows what to verify next with the utility, the authority and your engineers.

Frequently asked questions

What decides a data-centre site in India first?

The date and phasing of power from the state utility or transmission company. A nearby substation is a lead to verify, not a connection. Only a written answer from the utility counts.

Do Indian states have their own data-centre policies?

Several states, including Uttar Pradesh, Tamil Nadu and Maharashtra, publish data-centre or IT policies with incentives and approval routes. Check the current policy for the state and whether the site's land use qualifies.

Does Keystone prepare site studies for India?

Yes. Keystone prepares early data-centre site studies for India and the USA. Each finding is marked measured, assumed or not checked.