Keystone prepares early data-centre site studies for India and the USA. In India, a few checks decide most sites. Doing them in order saves spend on land that will not work.

The checks, in order
- Power date and phases. Ask the state distribution company or transmission utility when power can arrive, how much, and in what steps. A line or substation nearby is a lead, not a connection.
- State policy. Read the current data-centre or IT policy for the state. It sets incentives, approval routes and which land qualifies.
- Land use and building rules. Confirm the parcel's land use allows a data centre. Then apply the local development control rules: setbacks, ground coverage, FSI and height. Industrial land is a start, not a yes.
- Water and cooling. Find the supply source and the discharge route the cooling design needs, and what is confirmed in writing.
- Seismic and flood risk. Note the seismic zone under IS 1893 and check flood history and drainage for the plot.
- Access and fibre. Road access for heavy equipment, and the carrier routes near the site.
- Cost, timeline and returns. Only after the checks above, because each one moves these numbers.
What the study gives you
A comparison of campus options for the site, with power needs, cost range, timeline and estimated returns. Each finding is marked measured, assumed or not checked, so your team knows what to verify next with the utility, the authority and your engineers.