Show each hall’s IT load, estimated facility demand, utility milestones and the earliest opening supported by the available evidence.

Give each hall its own date
Set out when each hall needs power and how much IT load it is expected to support. Keep facility demand separate from IT load. Record assumptions for cooling and other supporting equipment so reviewers can see what drives the estimate.
Put the evidence beside the date
List the connection point, works that must be completed, responsible party and evidence date. Separate the first energisation milestone from the point when the planned load can be served. Where the utility has not confirmed a date or load, show it as open.
Compare what happens if power arrives later
Test whether the first phase can open at a lower load or on a later date. Carry that change through the layout, cost, construction sequence and estimated returns. Keep any commitments outside the site's control visible beside the option they affect.
What the study includes
A Keystone data center study compares site constraints, power evidence and campus options with cost, timing and estimated returns. Share the site boundary, phase brief and available utility records to start.
Read the full guide: data center site selection.