The ranked list
Gate: A no ends the site. Check these first.
- Power: firm MW and the date it arrives. Which utility serves the site, how many firm MW (and when, by phase), at what voltage, through which feeder and bay, with what upgrades and who pays?
- Land control and title. Who owns or controls the land, is the boundary surveyed, and what easements, liens, deed restrictions or rights of way sit on it?
- Permitted use and zoning route. Is a data center allowed here by right, by special permission or not at all, with which overlays, height, noise and setback limits? Zoning is not permission.
- Local and political standing. Are there pauses, pending ordinances, hearing opposition or public-disclosure rules on water and energy that could stall approvals?
- Flood and natural hazard exposure. What are the flood zone, drainage, seismic, wind, heat and fire exposures for this exact boundary?
- Water: supply, rights and discharge. How much water, from which source, with what right, quality and seasonal reliability, and where does wastewater go? Chosen together with the cooling method.
- Approvals path and timeline. Which environmental, pollution, fire, aviation, fuel and building approvals are needed, in what order, and how long does each take?
Size: Changes the layout, capacity or build.
- Net developable area. After deductions, setbacks, reservations, easements, wetlands and coverage limits, how much area can actually be built?
- Ground: terrain, soil, groundwater, contamination. What do survey, boreholes, groundwater level and a contamination review say about excavation, foundations and pad level?
- Access and logistics. Is there legal road access, with width, load limits, turning room, fire access, delivery routes and parking?
- Fibre and connectivity. Which carriers serve the site, with diverse entrances and routes, and what latency to the points the tenants need?
- Campus layout and phasing. Where do halls, plant, power rooms, fuel and roads go, what is built first, and how does expansion stay clear of live operation?
- Electrical design and backup. What are the intake, transformers, UPS, redundancy, generator rating at site conditions, backup fuel and the high-voltage route and rights?
- Cooling and efficiency. Which cooling method, what efficiency (PUE) and water use (WUE) at occupied load and by season, and what plant reserve?
- Capacity: IT load the site can hold. How many MW of IT load, at what rack density, fits in the placed halls, and what does not fit?
- Structure and coordination. Do frames, footings, equipment, maintenance clearances and fuel separation fit without clashes?
Price: Changes cost, schedule and return.
- Power price and energy cost. What is the tariff, with demand charges and escalation, at the load the cooling choice produces?
- Build cost per MW (range). What is the build cost as a range, from the placed quantities?
- Schedule to first power and opening. How long do utility works, equipment lead times, approvals and commissioning take, in sequence?
- Demand and tenant fit. Who would take this capacity, at what rent and ramp, and does the size and location match?
- Returns and financing. What is the return range, how does it move with cost, power price, delay and rent, and what financing route works?
- Incentives and taxes. What abatements or exemptions apply, and do they survive the approvals timeline?
Proof: Keeps every answer sourced, dated and consistent.
- Sources, freshness and conflicts. For every answer above: what source, what date, what conflicts, what is still unknown?
- Drawings, reports and numbers agree. Do the drawing, the quantities, the cost and the report say the same thing, in the same units?
- Check against real documents. Does the study match issued drawings and approvals, and does changing one input update everything that depends on it?
Four loops to solve together
- Power, cooling and water. The cooling method sets efficiency, which sets the power the site needs and the water it draws. Change one and the other two move.
- Land, layout, phasing and power. Net area limits how many halls fit. Phased power dates decide what is built first. Phase 1 can pass while the full campus fails.
- Approvals, schedule and returns. A slow approval moves the opening date, which moves the return.
- Gates before design. If a gate fails, stop before spending on the design checks.
What closes a check
A map, a listing, a stated MW figure, a nearby cable or a regional average does not close a check. A dated letter, a record for this parcel, or a measurement does. Mark each check closed, open or conflicting, with its source and date.
A Keystone study covers these checks for a site, with assumptions and missing evidence kept visible. See data center site selection and data centre feasibility for India and the USA.